7 | Consideration and Approval of Contract: Approve the construction contract with RTR Paving & Resurfacing, LLC in the amount of $1,699,908.00 for the Fourth Street Reconstruction project. | ||||||
Moved by Councilmember Charlie Odegaard, seconded by Vice Mayor Adam Shimoni to approve the construction contract with RTR Paving & Resurfacing, LLC in the amount of $1,699,908.00 and a contract duration of 250 calendar days, approve a contract allowance of $84,995.40, which is 5% of the lowest responsive bid, approve Change Order Authority to the City Manager in the amount of $169,990.80 which is 10% of the lowest responsive bid and authorize the City Manager to execute the necessary documents. | |||||||
Vote: 7 - 0 - Unanimously | |||||||