D | Consideration and Approval of Amendment One to the Construction Manager At Risk Construction Services Agreement: for the northern portion of the Coconino Estates Improvements Phase I Project. | ||||||
Capital Improvements Project Manager Eli Reisner provided a PowerPoint presentation that covered the following: CMAR CONSTRUCTION SERVICES AGREEMENT AMENDMENT ONE AMENDMENT ONE VICINITY MAP |
|||||||
Moved by Councilmember Charlie Odegaard, seconded by Vice Mayor Adam Shimoni to approve Amendment One to the Construction Manager At Risk (CMAR) Construction Services Agreement No. 2019-37, with Eagle Mountain Construction, to include the Guaranteed Maximum Price (GMP) for the northern portion of the Coconino Estates Improvements Phase I Project in the amount of $3,192,513.34 with no changes to the contract duration, approve an Owner’s Contingency of $74,842.99, which is approximately 2.3% of the Guaranteed Maximum Price for the northern portion of the Project, and authorize the City Manager to execute the necessary documents. | |||||||
Vote: 7 - 0 - Unanimously | |||||||