Consideration and Approval of Contract: Approve the construction contract with Western Utilities Contractors, LLC, dba Overley’s in the amount of $1,359,657.00 for the Summit Water project. |
|
|
|
Councilmember Whelan asked if the convenience rule could be used for the project to get the local respondent. Mr. Solomon explained that in accordance with the procurement manual, the rule would not apply to the project. |
|
|
Moved by Councilmember Jamie Whelan, seconded by Vice Mayor Adam Shimoni to approve the construction contract with Western Utilities Contractors, LLC, dba Overley’s in the amount of $1,359,657.00 and a contract duration period of 200 calendar days; approve a contract allowance of $67,982.85, which is 5% of the lowest responsive bid; approve Change Order Authority to the City Manager in the amount of $135,965.70 which is 10% of the lowest responsive bid; and authorize the City Manager to execute the necessary documents.
|
|
Vote: 7 - 0 - Unanimously |
|