B | Consideration and Approval of Contract: City of Flagstaff Municipal Court Facility Project - Award of Amendment #3 to the Design-Build Services Agreement 2018-63. This amendment contains the Guaranteed Maximum Price #3 agreement for completion of construction. | ||||||
Ms. Cameron provided a PowerPoint presentation that covered the following: CITY COURT FACILITY PROJECT TOPICS PROJECT LOCATION – 101 WEST CHERRY AVENUE PROJECT INFORMATION PROJECT ELEVATION DRAWING PHOTOS PROJECT BUDGET PROJECT SCHEDULE AMENDMENT #3 GMP #3 |
|||||||
Moved by Councilmember Jim McCarthy, seconded by Councilmember Jamie Whelan to award the Design-Build Services Amendment #3 Guaranteed Maximum Price (GMP) #3 to Kinney Construction Services, Inc. (KCS) of Flagstaff, Arizona in an amount not to exceed $545,478 with a 45 calendar-day contract period and authorize the City Manager to execute the necessary documents. | |||||||
Vote: 7 - 0 - Unanimously | |||||||